Shuqaiq Satellite Desalination Plant

Akon GrupShuqaiq Satellite Desalination Plant

Client: SWCC / Rawafid

Location: Shuqaiq, KSA

Project Start: Dec 2019

Project Duration: 10 Months

Expected Completion: Sep 2020

Peak Manpower: 250 people

Average Manpower: 208 people

Turnkey civil and architectural works for the Shuqaiq Satellite Desalination Plant Project.

Works included Sea Water Intake & Outfall, Pretreatment Area & Wastewater Area, RO Building, Electrical and Control Building, Post Treatment Area and Chemical Storage Building.

Scope included 56,531 m3 excavation, 92,370 m3 filling and 12,932 m³ concrete work.