Petrorabigh II – Initial Start Up Team Accommodation Project

Ongoing Project

Akon GrupPetrorabigh II – Initial Start Up Team Accommodation Project

Project No:  PRB008A

Client : Saudi ARAMCO / Sumitomo / Saudi
Arabian Baytur Co.

Location : Rabigh , K.S.A.

Project Duration : 243 days

Expected Completion : 29.03.2017

Peak Manpower : 343 people

Average Manpower : 200 people

Project Description

AKON International KSA is awarded Construction of Camp Facilities, 200 Bachelor Accommodation Units and 48 Family Residence Units. Including all MEP utilities and infrastructure works.

The project size;

  • Bachelor Units Covered Area – 54,580 Sq.m
  • Family Units Covered Area – 54,240 Sq.m

The scope of works include;

  • Structural works
  • Mechanical works
  • Electrical works
  • Plumbing works
  • Landscaping works