ÇUMRA PYROLYSIS POWER PLANT

Code : CPS028
Client : SUPRA
Country : TÜRKİYE
Location : Konya

Turnkey EPC Works for the Waste Tire Pyrolysis and Power Plant Project.

Project works included of design, supply, construction and electromechanical works.

Scope included EPC construction of 4 units of 15 tons/day pyrolysis reactor and auxiliary systems, 2 x 1.5MW HFO Engines and auxiliary systems, waste tire processing unit, switchyard, power transmission line and 0.5MW solar energy panel supply and installation. With the completion of the project, annually 15,000 tons of waste tire will be recycled to carbon black, steel wire and pyrolysis oil. 19,000,000 kWh of electricity will be generated annually by using the recycled pyrolysis oil as fuel for the installed engines.

08/2021

Start Date

01/2022

End Date

50000

Man Hour